SAP S/4HANA Production Planning and Manufacturing Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books | Weighting |
|---|---|---|
| Introduction to SAP S/4HANA Supply Chain Planning | Outline both motivation and background of SAP S/4HANA, describe its main components, the lines of business, and the SAP User Experience strategy. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Advanced Planning in SAP S/4HANA | Outline the basics and master data of advanced planning, explain tools (alert monitor, detailed scheduling planning board) and advanced planning and detailed scheduling processes, explain planning evaluation concepts TS421, TS422 (SAP S/4HANA 2020) | > 12% |
| Process Orders in SAP S/4HANA | Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP). TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Master Data in SAP S/4HANA | Identify and explain production relevant master data, including, but not limited to: bill of material, routing and production version. TS421, TS422 (SAP S/4HANA 2020) | > 12% |
| Material Requirements Planning in SAP S/4HANA | Select and apply planning strategies, use the planning table, characterize long-term planning and master production scheduling, outline MRP basics and steps of MRP, and describe lot size procedures. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Introduction to SAP S/4HANA Production Planning | Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Lean Manufacturing in SAP S/4HANA | Identify repetitive manufacturing specific master data, explain line load planning and confirmation, outline Kanban master data and Kanban processes. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Capacity Planning in SAP S/4HANA | Outline best practices for using SAP S/4HANA, describe the SAP HANA database concept and new user experience with SAP Fiori, outline the capabilities of embedded analytics. TS421, TS422 (SAP S/4HANA 2020) | 8% - 12% |
| Demand Management in SAP S/4HANA | Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning. TS421, TS422 (SAP S/4HANA 2020) | < 8% |
| Production Orders in SAP S/4HANA | Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation. TS421, TS422 (SAP S/4HANA 2020) | > 12% |
C_TS422_2020 Exam Certification Details:
| Languages: | English |
| Sample Questions: | SAP C_TS422_2020 Exam Sample Question |
| Exam: | 80 questions |
| Cut Score: | 56% |
| Level: | Associate |
| Duration: | 180 mins |
NEW QUESTION 37
What does a line hierarchy in repetitive manufacturing represent?
- A. A production line with a parallel sequence in the routing
- B. A production line with an alternative sequence in the routing
- C. A production line with more than one work center
- D. A production line with prioritized alternative work centers
Answer: C
NEW QUESTION 38
You want to triggering-houseproduction of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
- A. Make-to-order production (20)
- B. Planning without final assembly (50)
- C. Planning with final assembly (40)
- D. Planning at assembly level (70)
Answer: B
NEW QUESTION 39
What is the difference between co-products and by-products?
- A. Only co-products appear in the processor production order settlement rule.
- B. Only co-products are identified by a special item category in the bill of material (BOM).
- C. Onlyco-products can be manufactured in isolation from the main product.
- D. Only by-products have a zero inventory valuation.
Answer: A
NEW QUESTION 40
Which chart types does the tabular planning table provide in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Work center capacities chart
- B. Order (pool) chart
- C. Orders (dispatched) chart
- D. Capacity requirements chart
Answer: A,D
NEW QUESTION 41
Which time elements can be reduced by a reductionstrategy? Note: There are 3 correct answers to this question.
- A. Float after production
- B. Wait time
- C. Move time
- D. Goods receipt processing time
- E. Queue time
Answer: A,C,E
NEW QUESTION 42
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?
- A. When multiple production versions are maintained for one product
- B. When multiple planned orders exists in one resource
- C. When multiple operations are maintained for one product
- D. When alternate resourcesare used within one operation
Answer: D
NEW QUESTION 43
Your project team decides to use a make-to-order planning strategy for a strategic material in discretemanufacturing. What is the impact of this decision? Note: There are 3 correct answers to this question.
- A. Production orders are created with sales order reference.
- B. Sales order-specific stock is created
- C. Sales order-specific planning run is required.
- D. Storage location MRP areas are required.
- E. Net requirements calculation is sales order-specific.
Answer: A,B,E
NEW QUESTION 44
In your plant, MRP is activated. Which options do you have to exclude a material from the MRP run?Note:
There are 2 correct answers to this question.
- A. Use a specific material group
- B. Use a specific MRP type.
- C. Use a specific material status.
- D. Use a specific MRP controller.
Answer: B,D
NEW QUESTION 45
You want to create a production order from a planned order. What methods could you use? Note: There are 2 correct answers to this question.
- A. Individualconversion
- B. Full conversion
- C. Partial conversion
- D. Order release
Answer: B,C
NEW QUESTION 46
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.
- A. The work center has several individual capacities.
- B. The Change Planning Direct on indicator is set.
- C. Alternative resources are fully occupied.
- D. The planning strategy is infinite.
Answer: A,D
NEW QUESTION 47
What are the consequences if operation status Dispatched is set for a production order operation?
- A. You can reschedule the order using lead time scheduling.
- B. You canreschedule the order using material requirements planning.
- C. You can reschedule the operation using finite Scheduling in a planning board.
- D. You can reschedule the operation using lead the scheduling.
Answer: C
NEW QUESTION 48
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.
- A. Creation of dependent requirements
- B. Change of the storage bin
- C. Change of the material'sprocurement type
- D. Creation of a purchasing contract
- E. Creation of a sales order
Answer: A,C,E
NEW QUESTION 49
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note:There are 2 correct answers to this question.
- A. In-house production time
- B. Planned delivery time
- C. Total replenishment lead time
- D. Operation duration
Answer: A,B
NEW QUESTION 50
The MRP run detected a shortage of a material that you source from an external supplier in full pallets. How can you make sure you will only receive full pallets?
- A. Use the minimum order quantity.
- B. Use the MRP type for vendor managed inventory.
- C. Use the reorder point.
- D. Use the fixed lot size procedure.
Answer: D
NEW QUESTION 51
What data can you maintain in the sub items of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. Scrap percentage
- B. Installation point
- C. Item type
- D. Quantity
Answer: B,D
NEW QUESTION 52
What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question.
- A. Past quotation quantities
- B. Past procurement quantities
- C. One-off events
- D. Past sales order quantities
- E. Market intelligence
Answer: C,D,E
NEW QUESTION 53
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.
- A. To make the assignment of components easier
- B. To reduce the number of material masters
- C. To increase the number of planning levels
- D. To reduce the number of changes required in bills of material
- E. Tosimplify the structure of bills of material
Answer: A,D,E
NEW QUESTION 54
In a production process, you need acertain amount of liquid as input material. The source tank is directly connected to the reactor. How can you process consumption postings?
- A. Kanban
- B. Picking list
- C. Transfer Order
- D. Backflushing
Answer: B
NEW QUESTION 55
Which of the following business processes are controlled by parameters that are dependent on production order type? Note: There are 2 correct answers to this question.
- A. Engineering change management
- B. Planning
- C. Implementation
- D. Inspection during production
Answer: B,C
NEW QUESTION 56
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.
- A. Product-related
- B. Milestone-related
- C. Order-related
- D. Cost-related
Answer: A,C
NEW QUESTION 57
What is the purpose of collective orders?
- A. To post any component withdrawals single back flush with order confirmation
- B. To manage production orders for an entirefinished product on multiple levels
- C. To post production costs ona cost collector instead of the production order
- D. To combine order management of co-products and by-products with the main product
Answer: B
NEW QUESTION 58
When can the material availability check occur automatically in a production order? Note: There are 2 correct answers to this question.
- A. At order confirmation
- B. At order settlement
- C. At order creation
- D. At order release
Answer: C,D
NEW QUESTION 59
......
C_TS422_2020 Exam Dumps - Free Demo & 365 Day Updates: https://www.testpassed.com/C_TS422_2020-still-valid-exam.html
Pass C_TS422_2020 Exam with Updated C_TS422_2020 Exam Dumps PDF: https://drive.google.com/open?id=1f8XwPyAHaaw5yLjFJ5q6n-M4b3LLQWPQ