NEW QUESTION 27
Which of the following activities is an activity that will typically be performed as part of the Initiating phase of a test improvement cycle?
- A. Charter Infrastructure
- B. Develop Recommendations
- C. Plan Actions
- D. Analyse and Validate
Answer: A
NEW QUESTION 28
Which of the following statements is TRUE with respect to TMMi Levels 4 and 5 in an Agile context?
- A. Because Agile projects tend to focus on defect detection rather than defect prevention, Process area 5.1 Defect Prevention is less relevant when assessing an Agile organisation for TMMi level 5.
- B. Process area 4.3 Advanced Reviews is less relevant in an Agile context because quality tends to be a team effort and verification and validation tend to be discussed at team meetings, not in formal reviews.
- C. When considering the achievement of specific goals in process area 5.3 Test Process Optimization in an Agile context, the deployment of new testing technologies and test improvements do not have to be made across the whole organization, since Agile teams are autonomous and can decide which improvements suit their way of working best.
- D. Agile projects normally do not use operational profiles or usage models of a product on which to base statistically valid inferences to help create a representative sample of tests, thus the TMMi level 5 specific goal "Testing is performed using Statistical Methods" is considered not relevant in an Agile context.
Answer: C
NEW QUESTION 29
An informal TMMi assessment revealed a weakness in the area of traceability of test conditions and test cases to requirements.
Which process area are you be targeting when implementing the specific practice Maintain horizontal traceability with requirements?
- A. Test Monitoring and Control
- B. Test Design and Execution
- C. Test Lifecycle and Integration
- D. Test Planning
Answer: B
NEW QUESTION 30
Your organization performs code reviews and architectural reviews on a regular basis, in order to measure product quality early in the lifecycle.
This is an example of implementation of a specific practice from which TMMi level 4 process area?
- A. Product Quality Evaluation
- B. Quality Control
- C. Advanced Reviews
- D. Test Measurement
Answer: C
NEW QUESTION 31
Which of the following are NOT specific goals of the TMMi level 5 process area Test Process Optimization?
1. Select test process improvements
2. Determine, plan and implement test process improvements
3. Evaluate New Testing Technologies to Determine their Impact on the Testing Process
4. Deploy test process improvements
5. Monitor product quality against plan and expectations
- A. 3 and 5
- B. 1 and 4
- C. 2 and 5
- D. 2 and 3
Answer: C
NEW QUESTION 32
Which type of TMMi model component is described hereafter?
"The components guide those who implement improvements or perform assessments. Either the practices as described or acceptable alternatives to the practices must be present in the processes of the organization before goals can be considered satisfied."
- A. Alternative component
- B. Informative components
- C. Expected components
- D. Required component
Answer: C
NEW QUESTION 33
The three TMMi level 5 process areas, Defect Prevention, Quality Control and Test Process Optimization, all provide support for continuous process improvement.
Which of these process areas is specifically aimed at identifying new testing technologies that may be appropriate and to transition them into the organization?
- A. Quality Control
- B. Test Process Optimization
- C. All three level 5 process areas specifically address new testing technologies.
- D. Defect Prevention
Answer: B
NEW QUESTION 34
In a TMMi assessment, one of the shortcomings stated was the lack of professional testers. "Test functions and accompanying test career paths to be defined" is an improvement action recommended by the assessors.
Which TMMi process area addresses specific goals and specific practices for defining test functions and establishing test career paths?
- A. Test Training Program
- B. Test Organization
- C. Test Policy and Strategy
- D. Test Planning
Answer: B
NEW QUESTION 35
A test process assessment has been performed on a company developing systems for the medical industry.
Their systems are classified as safety critical. One of the shortcomings identified during the assessment is related to reliability testing. Although reliability was identified by the business as a critical issue, no formal approach and test techniques are being used for reliability testing.
Which of the following process areas would need specific attention to address the above mentioned shortcoming?
- A. Product Quality Evaluation
- B. Non-Functional Testing
- C. Test Environment
- D. Test Design and Execution
Answer: B
NEW QUESTION 36
The objective of a process area is to measure product quality early in the lifecycle, to enhance the test strategy and test approach by aligning static testing with dynamic testing, and to use the static testing results and data to optimize the test approach.
Which of the following process areas is concerned with this objective?
- A. Product Quality Evaluation
- B. Advanced Reviews
- C. Peer Reviews
- D. Test Measurement
Answer: B
NEW QUESTION 37
Which of the following statements is a correct description of the scope of the TMMi model?
- A. The TMMi model includes requirements for both formal and informal TMMi assessments.
- B. The TMMi model is specifically targeted at dynamic testing and does NOT address static testing.
- C. The TMMi model is intended to support testing activities and test process improvement in both the systems engineering and software engineering discipline.
- D. The TMMi model is specifically targeted towards higher test levels (e.g., system test and acceptance test).
Answer: C
NEW QUESTION 38
Advanced Reviews is a TMMi level 4 process area.
To which specific goal of the Advanced Reviews process area does the specific practice "Revise the product risks as appropriate" belong?
- A. SG 3 Adjust the Test Approach Based on Review Results Early in the Lifecycle
- B. SG 1 Coordinate the Peer Review Approach with the Dynamic Test Approach
- C. SG 2 Measure Product Quality Early in the Lifecycle by Means of Peer Reviews
- D. The specific practice "Revise the product risks as appropriate" is not related to a specific goal of the Advanced Reviews process area
Answer: A
NEW QUESTION 39
Which of the following process areas is a TMMi level 4 process area?
- A. Advanced Reviews
- B. Defect Prevention
- C. Test Lifecycle and Integration
- D. Test Policy and Strategy
Answer: A
NEW QUESTION 40
TMMi distinguishes between required, expected and informative components.
Which of the following is an example of an informative TMMi model component?
- A. Sub-practices
- B. Specific Practices
- C. Generic Goals
- D. Generic Practices
Answer: A
NEW QUESTION 41
Which of the following is a critical success factor that is typically most relevant while establishing improvements?
- A. Organize test improvement as a project
- B. The maturity of the development organization
- C. Management commitment
- D. Work on both long term and short term goals
Answer: D
NEW QUESTION 42
Which of the following components describe what an organization must comply with to satisfy a process area?
- A. Required components and expected components together
- B. Required components
- C. Informative components
- D. Expected components
Answer: B
NEW QUESTION 43
A test organization is trying to implement an improvement goal to develop a quantitative understanding of product quality, as part of the process area Product Quality Evaluation.
Which of the following specific practices needs to be addressed as part of process area 4.2 (Product Quality Evaluation) specific goal 1 Project Goals for Product Quality and their Priorities are Established?
- A. Measure product quality quantitatively throughout the lifecycle
- B. Identify product quality needs
- C. Identify non-functional product risks
- D. Establish test process measures
Answer: B
NEW QUESTION 44
......