NEW QUESTION 186
Who carries out audits that are independent of the project?
- A. Project Assurance
- B. Quality assurance
- C. Project Support
- D. Project Manager
Answer: B
NEW QUESTION 187
Who carries out audits that are independent of the project?
- A. Project Assurance
- B. Quality assurance
- C. Project Support
- D. Project Manager
Answer: B
NEW QUESTION 188
Which is one of the six aspects of project performance that needs to be managed?
- A. Risk
- B. Security
- C. Progress
- D. Change
Answer: A
NEW QUESTION 189
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
- A. Quality Register
- B. Configuration Item Record
- C. Highlight Report
- D. Checkpoint Report
Answer: D
NEW QUESTION 190
What theme provides the justification for the project?
- A. Plans
- B. Business Case
- C. Progress
- D. Quality
Answer: B
NEW QUESTION 191
Which is a PRINCE2 time-driven control?
- A. End Stage Report
- B. Project Initiation Documentation
- C. Project Brief
- D. Checkpoint Report
Answer: D
NEW QUESTION 192
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
- A. Specify the benefits of the project
- B. Specify the desired result
- C. Provide the resources and skills to deliver the desired result
- D. Pay for the project
Answer: C
NEW QUESTION 193
Why is a project brief produced?
- A. To record the how the project will communicate with its stakeholders
- B. To provide a full and firm foundation for the initiation of a project
- C. To act as a trigger for the 'starting up a project' process
- D. To be used by the project board as a basis for reviewing the progress of a project
Answer: B
Explanation:
Section: Volume B
NEW QUESTION 194
What theme defines and implements the means by which the project will verify that products meet business requirements?
- A. Business Case
- B. Quality
- C. Progress
- D. Change
Answer: B
NEW QUESTION 195
Which describes a risk event?
- A. The sequence of events and actions that will be put in place if a risk occurs
- B. The area of uncertainty in terms of the threat or opportunity
- C. The achievement of a milestone on the project plan
- D. The derivation or sources of a potential risk to the project
Answer: B
Explanation:
Explanation
Reference http://prince2.wiki/Risk
NEW QUESTION 196
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
- A. Write an Exception Report
- B. Raise an off-specification
- C. Raise a request for change
- D. Amend the Work Package
Answer: B
NEW QUESTION 197
When should the level of tailoring be defined?
- A. During the initiation stage
- B. When reviewing what has been learned to date
- C. Before the project is triggered by the project mandate
- D. As a response to issues and risks experienced
Answer: D
Explanation:
Explanation/Reference:
Reference https://www.prince2primer.com/tailoring-prince2-methodology/
NEW QUESTION 198
What is shown in a product breakdown structure?
- A. The resources that are required to develop the products
- B. Management stages, major products and control points
- C. The major products that are to be developed in a plan
- D. In which order the products should be created
Answer: C
Explanation:
Section: Volume B
NEW QUESTION 199
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
- A. a technical
- B. a corporate
- C. an external
- D. a temporary
Answer: D
NEW QUESTION 200
In which process is the work to be done assigned to a team manager?
- A. Directing a project
- B. Controlling a stage
- C. Managing a stage boundary
- D. Managing product delivery
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Controlling_a_Stage
NEW QUESTION 201
Which is a typical core activity within configuration management?
- A. Risk management
- B. Verification and audit
- C. Quality assurance
- D. Progress reporting
Answer: B
NEW QUESTION 202
What is an off-specification?
- A. A major risk
- B. A new requirement
- C. A type of issue
- D. A quality tolerance
Answer: C
NEW QUESTION 203
From whom does a Team Manager obtain approval for a completed product?
- A. The authoritydefined in the Product Description
- B. Senior Supplier
- C. Project Support
- D. Project Manager
Answer: A
NEW QUESTION 204
Which statement about risks is FALSE?
- A. A risk that could have a positive impact on a project's objectives is known as an opportunity
- B. A risk that a project's product is incomplete is known as an off-specification
- C. A risk is an uncertain event that, should it occur, will have an effect on a project's objectives
- D. A risk that could have a negative impact on a project's objectives is known as a threat
Answer: B
NEW QUESTION 205
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
- A. Progress
- B. Organization
- C. Quality
- D. Change
Answer: A
NEW QUESTION 206
Where should decisions regarding the tailoring of the project be recorded?
- A. Stage plan
- B. Project initiation documentation
- C. Project brief
- D. Project mandate
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 207
......
Authentic Best resources for PRINCE2Foundation Online Practice Exam: https://www.testpassed.com/PRINCE2Foundation-still-valid-exam.html
PRINCE2Foundation Test Engine Practice Exam: https://drive.google.com/open?id=1ebC4ZTBwlg_f2OmazRoW_8FlWOwy0BgO